Resources and Resource Usage

The Resources section of your chart is split into two panels:

  • Resources - Displays a list of all resources based on the information entered into the field you assigned for resources.
  • Resource Usage - Displays the work load for each resource at a given time.

Resource Panels in Structure.Gantt

You can also display the allocation numbers in the Gantt chart itself. To do that, simply group your tasks by the attribute you used to define the resources.

Hidden Resources

You may only see a limited number of available resources listed here if:

  1. The structure has been filtered - in this case, the Resource panel will only include those resources assigned to the items left in the structure
  2. Resource Filtering has been applied

Overallocation

If there is more work assigned to a resource than the resource can handle, the Usage square for that block of time will be highlighted (See Anna M's usage above). This allows you to quickly identify places where you may need to revisit your timeline or work distribution.

Resource Usage Timeline

The Resource Usage timeline aligns with the Gantt chart timeline above and adapts to the zoom level selected in the Gantt toolbar. Zoom in or zoom out to see details of allocation within a specific period.

To learn more about assigning resources to tasks, see Resources Configuration.

Hours vs Percentage

Resource usage can be displayed in one of two ways:

  • the number of hours assigned to a resource for a set period of time
  • the percentage of a resource's availability (as determined in Resource Settings) that is being used at a given time

To change how resource usage is displayed, simply click on the drop-down menu in the upper-right corner of the Resource Usage panel.

Display resource usage as hours or percentage

Depending on your zoom level and work schedule, chart cells may appear the same but contain different amounts of work. For example, with a 6-hour zoom, you will see two cells for a typical work day (6am-12pm and 12pm-6pm), but if your work day is from 9am-5pm, the first cell will only represent 3 hours of work, while the second represents 5 hours. This is perfectly normal and does not impact the percentage of availability in any way.