Viewing Saved Baselines
To compare the current chart to a saved baseline, open the Baseline menu and select the baseline you wish to use.
![Open an existing baseline Open an existing baseline](/documentation/gantt/files/latest/cloud/160530507/160530512/1/1669038063000/Open+Baseline_Cloud.png)
Baseline Offset
When viewing a chart with a baseline, hover over any item to see how far ahead or behind the baseline schedule the task currently is.
![Baseline offset Baseline offset](/documentation/gantt/files/latest/cloud/160530507/160530511/1/1669038063000/Baseline+Offset_cloud.png)
Hiding Baselines
When a baseline is applied, it's name is displayed in the Baseline menu.
![](/documentation/gantt/files/latest/cloud/160530507/160530517/1/1669038063000/Current+Baseline.png)
To hide the baseline (so you just see the current chart), open the Baseline menu and click No Baseline.
![](/documentation/gantt/files/latest/cloud/160530507/160530518/1/1669038063000/No+Baseline.png)
Exporting Baselines
You can include baselines when exporting a Gantt chart.
![Export Gantt to PDF Export Gantt to PDF](/documentation/gantt/files/latest/cloud/160530507/160530510/1/1669038063000/Exported+Structure+with+Baselines_cloud.png)
To include baselines in an export:
- Make sure the baseline you want to include is visible in the chart before selecting Export Gantt Chart
- Check the Baseline option in the Gantt Chart Details section of the Export dialogue
- Select whether or not Baseline delays should be displayed