Message-ID: <1013093582.16206.1711728156402.JavaMail.appbox@confluence> Subject: Exported From Confluence MIME-Version: 1.0 Content-Type: multipart/related; boundary="----=_Part_16205_733605221.1711728156402" ------=_Part_16205_733605221.1711728156402 Content-Type: text/html; charset=UTF-8 Content-Transfer-Encoding: quoted-printable Content-Location: file:///C:/exported.html Running Resync

Running Resync

A resync, or full resynchronization, is a one-time process activ= ated manually by the user to bring Structure and some other aspect of issue= s to the same page. Resync typically scans all issues that may be affected = - contrary to the incremental synchronization, which inspects only issues t= hat have been changed.

=20

For example, running resync on a Saved Filter synchronizer (in Add mode) runs the related Saved Filter and makes sure all issues from= the result set are in the structure. When the same synchronizer is working= in the background, it checks only those issues that have been changed.

= =20
Resync Directions
=20

Resync is also different from incremental synchronization in that it has= a direction. The incremental sync tries to apply changes on both&= nbsp;sides to the other side, if possible, depending on where the change ha= s happened: with JIRA Agile (GreenHopper) synchronizer, if you change the r= ank (issue position in backlog on the Planning Board), its position in the = structure is also changed; and if you change the position in the structure,= GreenHopper's rank is changed. However, when applying Resync, you need to = choose which side of the data is to be taken as the final version and which= is to be updated.

=20

Resync can be run:

=20 =20

A synchronizer may support resyncing in only one direction. For example= , Saved Filter synchronizer, which adds issues from a saved filter result, = can only sync into Structure.

=20
Running Resync
=20

To run a resync:

=20
    =20
  1. Open Manage Structure page using top navigation S= tructure
  2. =20
  3. Click Settings link in the Sync With column f= or your structure
  4. =20
  5. On the synchronization settings page, find the synchronizer you'd like = to Resync, and either=20
      =20
    1. Click Resync
    2. =20
    3. Click Resync and Enable if the synchronizer is disable= d and you'd like to enable it immediately after Resync finishes
    4. =20
  6. =20
  7. Select a direction for the Resync. For example, JIRA Agile (GreenHopper) =E2=86=92 Structure means that the data will be taken f= rom JIRA Agile and the structure will be rearranged. If a direction is not = supported by the synchronizer, it will be disabled.
  8. =20
  9. Click Start Resync.=20

    Resyncing in a wrong direction may lead to data loss! Please make sure y= ou understand that you're doing the correct thing and confirm running the r= esync when a confirmation dialog appears.

  10. =20
  11. The job status page that appears will tell you when the Resync has fini= shed.
  12. =20
=20

If the synchronizer is currently running an incremental synchronization,= the resync will wait until it finishes.