Page History
Default structure is selected when the user opens Structure Board for the first time, or when the Auto-switch option is set to default structure. You can change the default structure for the JIRA instance and for a specific project.
Changing system-level default structure
- Open Administration | Structure | Defaults menu.
- In the System Default Structure section, click Change.
- Select the default structure and click Apply.
The new system-level default structure will be also default for all structure-enabled projects that don't have this setting overridden.
Note |
---|
Make sure that default structure has correct permissions. If the structure is selected for the user by default, but the user does not have |
Changing project-level default structure
- Open Administration | Structure | Defaults menu.
- Locate the project in the Project Default Structures section. Un-check Show only projects with overridden default structure checkbox if needed. Click Change in the corresponding row.
- Select a structure and click Change.
- or, select Use system default to remove the project-level default.
Project administrator can also change project-level structure from the Structure tab on the project administration page, or from the options pop-up window on the Structure tab on the user's project page.