You can use Time Tracking, Story Points or both as tasks duration. To define this, please use the Gantt configuration.

If no estimate is set, the default duration from the configuration is used.

To adjust duration, mouse over the right end of the task bar and once the mouse pointer changes to the resize tool, click and drag left or right to set the desired duration. In Structure.Gantt, duration for each task can be calculated in one of three ways.

Automatically

When tasks are automatically scheduled or manually scheduled without a fixed duration, their duration is calculated automatically, based on their work estimates and the Work Estimates settings associated with that task.

To adjust the duration of these tasks:

  • Edit the task's work estimate fields, or
  • Drag the left or right side of the task bar.
    Image Added

Dragging Automatically Scheduled Tasks

If you drag the right side of a task that is automatically scheduled, the task remains in automatic scheduling mode, but its duration is updated. If you drag the left side of the task, the task becomes manually scheduled based on the new Start Date and it's duration is updated accordingly.

In either case, the duration will be updated as follows:

  • If you are using Jira Time Tracking, the Original Estimate field value will be updated (for issues with no time logged

...

  • ) or the Remaining Estimate field value will be updated (for the issue with time logged

...

  • )
  • If you selected Prefer Custom Estimate over Time Tracking for Work Estimates, the value in the custom estimate field will be adjusted based on the ratio defined in the configuration.

You can also adjust duration by changing the value of the Jira fields themselves.

Info

If you have both Start and End dates defined, duration will be ignored and resizing the bar will affect the Finish date instead.

Dragging Manually Scheduled Tasks

When you drag the side of a manually scheduled task, if the side of the task you are dragging was manually scheduled, the corresponding field (Start or Finish Date) will be updated to the new date and the duration will be updated accordingly. Otherwise, only the duration will be updated.

In either case, the duration will be updated as follows:

  • If you are using Jira Time Tracking, the Original Estimate field value will be updated (for issues with no time logged) or the Remaining Estimate field value will be updated (for issues with time logged)
  • If you selected Prefer Custom Estimate over Time Tracking for Work Estimates, the value in the custom estimate field will be adjusted based on the ratio defined in the configuration.

Based on Start and Finish Dates

When tasks are manually scheduled and have both a manual Start and Finish Date, the task has a fixed duration, spanning the time between its Start Date and Finish Date.

To adjust the duration of a fixed duration task, drag either side of the task bar. This will update the task's Start or Finish Date, and the duration will be adjusted accordingly.

Image Added

Info
Adjusting the duration of a fixed duration task does not affect its work estimate.

Based on Sprints

When tasks are scheduled based on sprints, they have a fixed duration corresponding to the length of the sprint. It is not possible to adjust the duration of these tasks, except by removing them from sprint-based scheduling or changing your sprint duration settings.