Structure.Gantt allows you to configure how progress for individual tasks and groups is calculated.

Progress settings

By default, progress is calculated using the same settings as Work Estimates Configuration. In this case, progress will be calculated based on the values (Time Tracking, Story Points, etc.) you selected in the Work Estimates section.

If you prefer, you can specify a different field from Work Estimates.


If you prefer, you can specify a different field from Work Estimates or use a Formula for progress calculation.



While using Time Tracking, tasks with non-empty resolutions are treated as 100% complete.


While using Time Tracking, tasks with non-empty resolutions are treated as 100% complete. If using a Formula, it should return values from 0 to 100. All values higher than 100 will be treated as 100. (Hint: if your formula only returns values between 0 and 1, multiply by 100.)



A group's progress is always calculated based on the provided values for its tasks, regardless of the Progress field selected. See below.

Progress Calculation

When Time Tracking is used, a task's progress is calculated in the following way:

When Story Points are used for work estimation, a task's progress is calculated in the following way:

For groups, the progress is calculated as a total progress of all unique tasks within the group: