In Structure.Gantt, dependencies are defined based on Issue Links. Changing dependencies creates or removes links between issues (the link type is defined in the Gantt configuration).
Structure.Gantt supports Finish to Start, Start to Start, Finish to Finish and Start to Finish dependencies.
Structure.Gantt uses Finish to Start dependencies by default. To enable other types of dependencies, see Gantt Configuration | Dependencies.
To create a Finish to Start dependency:
To create other types of dependencies:
If you haven't configured a Dependency Type, you won't be able to select it in the New Dependency menu. To configure dependency types, see Gantt Configuration | Dependencies. |
To view the details of an existing dependency, click the link arrow connecting two tasks.
To delete a dependency, click the Remove link in the Dependency Properties panel.
Next Step: Gantt Chart Elements