Structure.Gantt highlights any scheduling conflicts with a dark red line placed on top of the task bar. To review and resolve the conflict, open the Task Details panel. The conflict will be explained at the bottom of the panel, along with resolution options.
Issue dependencies may create conflicts when manual scheduling is enabled. For example, for finish-to-start dependencies, if a task is scheduled for a date earlier than its predecessor's Finish Date, Structure.Gantt will highlight this conflict.
To deal with the conflict, click the task and select one of the following actions:
Ignore - Tells Structure.Gantt to ignore the conflict. If additional changes are made to the task and the conflict still exists, the red line will reappear. |
When sprint-based scheduling is used, dependent issues in the same sprint will not be marked as a conflict, since they can be completed at any point during the sprint.
|
If a task is scheduled for a fixed duration shorter than its work estimate, you will receive an error message.
When this occurs, you have a few options to resolve the conflict:
If Prefer sprints over manual start and finish dates is selected in your Gantt configuration, the Increase Duration option will be unavailable, because changing the start date would have no effect when sprints take precedence. |