Calculating Progress for Issue Without Sub-Issues
If the issue does not have sub-issues:
- If the issue's Resolution field is not empty, the progress is 100%.
- Otherwise, the progress is 0%.
Calculating Progress for Issue with Sub-Issues
If the issue does have sub-issues:
- If the issue's Resolution field is not empty, the progress is 100% - regardless of the sub-issues progress.
- Otherwise, sub-issues progress is aggregated sum with specified weights.
Example: Resolution Only with Story Points
Individual progress is 0% or 100% based on Resolution field; total progress is calculated as weighted average, with weights contained in a Story Points field.
Column Configuration
Sample Structure
Issue | Explanation | Progress |
---|---|---|
Sub-sub-issue 1.2 | This issue is resolved (indicated by the green mark) - so it is complete | 100% |
Sub-issue 1 | It has two sub-issues with 0% and 100% progress, and story points are 2 and 3 respectively. So the total progress is weighted average value of (0 x 2 + 100 x 3) / (2 + 3) | 60% |
Top issue | It has two sub-issues: sub-issue 1 is 60% done and sub-issue 2 is 0% done, and their cumulative story points are (2 + 3) and 1 respectively. So progress is (60 x 5 + 0 x 1) / (5 + 1) | 50% |