The progress is determined by issue's Status field. Percentage values are assigned to specific statuses.
Calculating Progress for Issue Without Sub-Issues

If the issue does not have sub-issues:

  • If the issue's Resolution field is not empty, and Apply Resolution is turned on, the progress is 100%.
  • If the issue's Status is assigned a value (%) in the column configuration, the progress is equal to that value.
  • Otherwise, the progress is undefined, so the issue neither shows any progress, nor affects the progress of its parent issue.
Calculating Progress for Issue with Sub-Issues

If the issue does have sub-issues:

  • If the issue's Resolution field is not empty, and Apply Resolution is turned on, the progress is 100% - regardless of the sub-issues progress.
  • Otherwise, sub-issues progress is aggregated sum of progresses with chosen weights.

If the issue has both its own status and sub-issues with progress, and if Ignore Parent Issue Progress is turned off, issue's own progress value is counted as if was the progress of one another sub-issue.

If some of statuses don't have any percentage configured, issue progress is considered undefined.

 

Example: Progress Based on Status, All Sub-Issues Are Equal

In this example, statuses have the following percentages: Open = 0%, In Progress = 50%, Resolved or Closed = 100%, Reopened = 80%. Apply Resolution is turned on, Ignore Parent Issue Progress is turned on.

Column Configuration


Sample Structure

 

Issue

Explanation

Progress

Sub-sub-issue 1.1

This issue is Open, so it is 0%

0%

Sub-sub-issue 1.2

This issue is In Progress, so it is 50%

50%

Sub-sub-issue 1.3

This issue is Resolved, so it is 100%. Also, according to workflow, it has non-empty Resolution, which also means it's complete.

100%

Sub-sub-issue 1.4

This issue is Close, so it is 100%. Also, according to workflow, it has non-empty Resolution, which also means it's complete.

100%

Sub-issue 1

Average progress is (0+50+100+100)/4. Issue's own status is In Progress, but it's percentage is ignored because of "Ignore parent issue progress in aggregation" option

63%

Sub-sub-issue 2.1

This issue is Reopened, so is 80%

80%

Sub-sub-issue 2.2

This issue is Open, so is 0%

0%

Sub-issue 2

Average progress is (80+0)/4 = 40%. But issue itself has Resolution and "Issues with Resolution are 100% done" option is turned on, so this overrides sub-issues progress and makes issue complete

100%

Top issue

It has two sub-issues: sub-issue 1 is 63% done and sub-issue 2 is 100% done. Average progress is (63+100)/2

82%